George Lane Viaduct

14 January 2026 Rhinoceros bricklayers complete the rebuilding of a 24 metre section of the parapet wall to the Viaduct at South Woodford. This is a three brick thick wall. We used over 3000 Swanage Red Imperial bricks. The original cast concrete with black stone chippings coping stones were reinstalled set on Sika Monotop mortar

Previous
Previous

DLR 3 Span Bridge Silvertown

Next
Next

Griggs Approach Ilford